Google acquired the site Crusoe had been preparing for a data centre in southeast Wyoming, Crusoe announced on 6 November. A day earlier, Google had unveiled a $17 billion investment plan for its first data centre in the state. That figure refers to the investment; the companies did not announce it as the purchase price.
Crusoe says it had worked on site selection, government approvals and a mix of power sources with Tallgrass Energy. Reuters and TechCrunch separately reported the transfer. The new development is a change in who owns the site, while the infrastructure Google described is still under development.
Power is part of the project
Google says it has contracted with American Electric Power for a planned 702 MW fuel-cell installation. The cells will use natural gas, with the project designed to capture and store underground a large share of the plant’s emissions. Google also plans to air-cool the data centre and is studying whether carbon capture can be fitted to separate Tallgrass turbines.
The acquisition shows how closely computing capacity is tied to access to land, permits and electricity generation. The 702 MW figure describes a planned installation, not current output. The expectations for emissions and water use are also based on the design. Performance can be measured once the facility is operating.
Our sources
- Google Acquires Crusoe’s Wyoming Data Center Site ↗Crusoe · 6 November 2026 · Checked 8 November 2026
- Google’s data center investment in Wyoming ↗Google · 5 November 2026 · Checked 8 November 2026
- Google acquires Wyoming data center site from Crusoe ↗Reuters · 6 November 2026 · Checked 8 November 2026
- Crusoe sells troubled Wyoming data center project to Google ↗TechCrunch · 6 November 2026 · Checked 8 November 2026
AI tools assist our editors. Articles are published after human approval. Practical examples are ΠΕΡΑ analysis unless stated otherwise. How we work